CEB SOLAR PHOTOVOLTAIC SCHEME (HOUSEHOLDS) Grid Code — Greater than 50 kW and not exceeding 500 kW — Central Electricity Board
The purpose of this document is to assist the public to better understand the procedure for application, the requirements of the SSDG Grid Code and other related issues regarding the Small Scale Distributed Generation (SSDG) Project.
Any prospective applicant willing to take advantage of the Small Scale Distributed Generation (SSDG) Scheme is informed that:
The Central Electricity Board’s (CEB’s) “Grid Code for Small Scale Distributed Generator (SSDG)”, including any periodic revisions, published on the CEB website, constitute the minimum technical requirements for the connection of Distributed Generation (DG), with or without Battery Energy Storage System (BESS), to CEB’s low voltage distribution network. The active power injection of DG shall at no time exceed 50 kW ac at the Supply Terminal as measured by the Import / Export meter of the CEB or the maximum scheme capacity as applicable at the time.
The owner of the SSDG may be required to meet additional requirements to ensure that the interconnection meets all local regulations and is safe for use. The requirements set in this Grid Code are based on system conditions that may be subject to change. As such, these requirements shall only be used as a guide. The use of this Grid Code and the information it contains is at the user’s sole risk. Neither CEB, nor any of its personnel, makes any warranties or representations of any kind in connection with this Grid Code, including its correctness, accuracy, completeness or adequacy for any specific purpose. CEB will not be responsible or liable for any damage or loss that may arise due to the use of the Grid Code, reliance on the information it contains, or any decisions made based on the Grid Code. CEB reserves the right to revise this Grid Code at any time.
The CEB reserves the right to modify such technical specifications and requirements of the SSDG system before or during implementation of the SSDG connection process, in order to adhere to the latest operational and safety aspects of the network. The SSDG installation shall abide with the latest SSDG Grid Code and standards at the time of implementation of the project.
| Version | Date | Changes |
|---|---|---|
| Version 2.3 | September 2019 | Minor revisions |
| Version 3.0 | April 2026 | Requirements for SSDG with Battery Energy Storage System (BESS) included |
The Grid Code describes the technical criteria and requirements for interconnection of Small Scale Distributed Generators (SSDG) with CEB’s low voltage (230/400 V) network systems.
The Grid Code caters for the production of electricity and its storage from inverter-based renewable energy sources such as photovoltaic.
The Grid Code addresses connections of electricity producers under the SSDG Schemes. More details on the schemes are available on CEB website at ceb.mu/projects/energy-schemes.
All DGs with export capacity less than 5 kWac shall have either single phase or three phase output. All DGs with export capacity of 5 kWac and above, shall have three phase output only.
All inverters shall be of Grid Forming type.
The DGs shall be connected to the 230/400 V system and operated within the parameters as listed in Table 1 below. The DGs have to be functioning and protect itself within the range of the voltage, current and frequency existing in the CEB’s grid.
| Description | Range |
|---|---|
| Voltage | 230/400 V ± 6 % |
| Short Circuit Characteristics | (1 sec) 18 kA, (50 Hz) |
| Nominal Frequency | 50 Hz |
| Statutory Frequency Deviation | 50 Hz ± 1.5 % |
| Operating Frequency Range | 47 Hz – 52 Hz |
The CEB LV grid is designed as a TT system. The above values are mandatory for all DGs. Same requirements apply for DG with Battery Energy Storage System.
Subject to the requirements of the prevailing scheme, the DG capacity shall also be limited to the technically permissible DG connection capacity of the distribution transformer feeding the customer. Should there be other DGs connected on the same distribution transformer, the total capacity of all these shall be taken into consideration for the acceptance of an SSDG application.
The coordination and selectivity of the protection system must be safeguarded even with the entrance of new generation into the system. To guarantee this requirement, the protections to be installed are listed in the following chapters and the settings of those protections shall conform at minimum to the requirements of the Grid Code.
In case of short circuits on the DG’s side of the Supply Terminal, the SSDG shall adjust its protections in such a way that will avoid unnecessary trips and at the same time avoid that the incident propagates to the CEB LV network.
In case of incidents originating external to the DG, like short circuits on CEB’s side of the Supply terminal i.e. the CEB LV network, fluctuations of frequency or voltage, DG will give priority to the network protection to clear the incidence and act accordingly with the coordination and selectivity principles of the protections system.
The applicant shall ensure that all equipment is protected and that all elements of the protection, including associated inter-tripping, are operational at all times. Failure of the protection will require the DG to be taken out of service.
The DG shall be protected against:
A DG should be equipped with all necessary protection systems, as recommended by the manufacturer and relevant international standards, to ensure that all the equipment and apparatus powered by the DG operate within their technical limits.
All protection apparatus functions shall operate down to a level of 50% of the nominal DC supply voltage of the DC system, or the system must be able to safely disconnect and shutdown when operation conditions are outside the nominal operating DC voltage specified in the DC system specifications.
All protective devices supplied to satisfy the CEB’s requirements shall be equipped with operation indicators. Such indicators shall be provided to enable the identification of which devices caused a particular trip.
Any failure of the applicant’s tripping supplies, protection apparatus and circuit breaker trip coils shall be supervised within the applicant’s installation, and the applicant shall be responsible for prompt action to be taken to remedy such failure.
The basic trip settings for grid-tied DG must comply with the values stated in Table 2. However, for DG configured for islanding operation with no export to the grid, the trip settings shall nevertheless be implemented to cater for switch in operation mode due to malfunction or human intervention. The trip setting may be modified as per CEB’s request on a case-to-case basis.
Note: Voltage and frequency are referred to at the Supply Terminals.
| Parameter | Symbol | Trip Setting | Clearance Time |
|---|---|---|---|
| Over Voltage (a) | U>> | 230 V + 10 % | 0.2 s |
| Over Voltage | U> | 230 V + 6 % | 1.5 s |
| Under Voltage | U< | 230 V − 6 % | 1.5 s |
| Over Frequency (b) | f> | 50 Hz + 1.5 % | 0.2 s |
| Under Frequency | f< | 50 Hz − 6 % | 0.5 s |
| Loss of Mains | df/dt & Vector Shift | 2.5 Hz/s & 10° | 0.5 s |
(a) If the DG can generate higher voltage than the trip setting, the step 2 over voltage (U>>) is required.
(b) The trip setting for over frequency is set lower than the maximum operating frequency defined in Table 1 in order to avoid contribution of the DG to rising frequency.
DG without Battery Energy Storage System shall not supply power to the CEB’s network during any outages. It may only be operated during such outages to supply the applicant’s own load (isolated generation) with a visibly open tie to the CEB’s network. The DG shall be disconnected from the CEB’s network within 0.2 seconds of the formation of an island as shown in Table 2.
DG with Battery Energy Storage System can operate in islanding mode. However, if it is operating in grid tie mode exporting power to the CEB’s network it shall disconnect from the CEB’s network within 0.2 seconds of the formation of an island as shown in Table 2.
Following a protection-initiated disconnection, the DG is to remain disconnected from the network until the voltage and frequency at the supply terminals has remained within the nominal limits for at least 3 minutes under grid tied mode. Automatic reconnection is only allowed when disconnection is due to operating parameters being outside the normal operating range stated in Table 1, not if disconnection is caused by malfunctioning of any devices within the DG installation.
The DG shall provide and install automatic synchronizing features. Check Synchronizing shall be provided on all generator circuit breakers and any other circuit breakers, unless equipped with appropriate interlock, that are capable of connecting the DG to the CEB’s network. Check Synchronizing Interlock shall include a feature such that circuit breaker closure via the Check Synchronizing Interlock is not possible if the permissive closing contact is closed prior to the circuit breaker close signal being generated by close command being activated.
Earthing shall be according to IEC 60364-5-55.
For systems capable of operating in isolated generation, protection by automatic disconnection of supply shall not rely upon the connection to the earthed point of the utility supply system. When a DG is operating in parallel with the CEB’s network, there shall be no direct connection between the cogenerator winding (or pole of the primary energy source in the case of a PV array or Fuel Cells) and the CEB’s earth terminal.
A DC source or DC generator could be earthed provided the inverter separates the AC and DC sides by at least the equivalent of a safety isolating transformer. However, consideration would then need to be given to the avoidance of corrosion on the DC side.
At the CEB’s grid TT earthing system is normal. The neutral and earth conductors must be kept separate throughout the installation, with the final earth terminal connected to a local earth electrode.
Warning: Notice that “CONDUCTORS MAY REMAIN LIVE WHEN ISOLATOR IS OPEN” shall be conspicuously displayed at the installation.
The DG should not inject a Direct Current greater than 0.25 % of the rated Alternating Current output per phase.
The DG installation shall not cause abnormal flicker beyond the limits defined by the “Maximum Borderline of Irritation Curve” specified in the IEEE 519-2014.
Based on IEEE 519, the Total Harmonic Distortion (THD) Voltage shall not exceed 5.0% of the fundamental on 400 V when measured at the Point of Common Coupling (PCC).
The total harmonic distortion will depend on the injected harmonic current and the system impedance seen from the PCC. However, in order to facilitate the fulfilment of the requirements by e.g. inverter manufacturers, the voltage distortion limits have been translated into a similar requirement on current distortion.
The DG output should have low current-distortion levels to ensure that no adverse effects are caused to other equipment connected to the utility system. The DG electrical output at the PCC should comply with Clause 10 of IEEE Std. 519-2014. The key requirements are:
| Odd Harmonics | Maximum Harmonic Current Distortion |
|---|---|
| 3rd – 9th | 4.0 % |
| 11th – 15th | 2.0 % |
| 17th – 21st | 1.5 % |
| 23rd – 33rd | 0.6 % |
| Above the 33rd | 0.3 % |
The interconnection system shall have a surge withstand capability, both oscillatory and fast transient, in accordance with IEC 62305-3 at test levels of 1.5 kV. The design of control systems shall meet or exceed the surge withstand capability requirements of IEEE C37.90.
The connection of unbalanced loads and generation to the distribution network can result in unbalanced currents and voltages. DG that uses 3-phase generators or inverters which inject balanced currents into the distribution network do not increase levels of voltage imbalance in the network. In fact, embedded generators which use 3-phase induction generators can actually reduce voltage imbalance.
The total voltage unbalance in the grid should be smaller than 2%, where the unbalance Uunbalance is defined as the maximum deviation from the average of the three-phase voltages Ua, Ub and Uc, divided by average of the three-phase voltages:
The contribution from one installation may not cause an increase of the voltage unbalance of more than 1.3%.
When considering three phase units, the contribution to the voltage unbalance can be described as:
Where:
If nothing else is stated, Ssc shall be 2.5 MVA. The demand on voltage unbalance on a three phase load can be translated into a demand on the maximum negative sequence current:
The process of starting a DG can cause step changes in voltage levels in the distribution network. These step changes are caused by inrush currents, which may occur when transformers or generators are energised from the network. Step voltage changes will also occur whenever a loaded generator is suddenly disconnected from the network due to faults or other occurrences.
Step voltage changes caused by the connection and disconnection of generating plants at the distribution level should not exceed ±3% for infrequent planned switching events or outages and ±6% for unplanned outages such as faults.
If the connection of the DG to the grid does not exceed the following values in Table 4, it is expected to stay within the above-mentioned voltage levels.
| Connection | Inrush Current |
|---|---|
| Single phase | 19 A |
| Three phase | 30 A |
The power factor of the DG at normal operating conditions across the statutory range of nominal voltage shall be between 0.95 leading and 0.95 lagging.
The Preventive and Corrective maintenance of the feeder where the DG is connected may interrupt the DG’s generation. No compensation shall be applicable for the loss of generation.
According to the CEB Safety Rules based on the Occupational Safety and Health Act 2005, the following rules, amongst others, must be respected before working on the grid:
Isolation for a DG without Battery Energy Storage System (BESS) shall be as per Figure 1.
For a DG with Battery Energy Storage System (BESS), indicative layout is shown in Figure 2. The system shall be designed to enable the CEB to install the required energy meters necessary to comply with the Renewable Energy (RE) scheme under which the application has been submitted.
The DG owner shall observe the following safety concerns:
The DG shall comply with the requirements of the EMC Directive and in particular the product family emission standards.
To indicate the presence of the DG within the premises, the CEB shall fix a label at:
For DG with or without Battery Energy Storage System, a label as per Figure 3 will be used:
The installation operating instructions must contain the manufacturer’s contact details e.g. name, telephone number and web address.
Up-to-date information must be displayed at the DG as follows:
The following information shall appear on the information plate for PV system:
For Battery Energy Storage System (BESS) the following information shall appear on the information plate:
The DG shall be installed in accordance with the instructions issued by the manufacturer. In designing a connection for a DG, the electrical contractor/installer must consider all the issues that would need to be covered for a conventional final circuit, including:
The installer must affix a label clearly indicating the next scheduled maintenance of the installations and inform the CEB, who will add the information to the SSDG-register.
The installer must be skilled in the field of DG including Battery Energy Storage System and possess a relevant and approved certificate.
In order to calculate the export or import of the applicant, a bidirectional meter (Import/Export Meter) measuring both the imported and exported energy shall be installed.
A second meter measuring the gross energy production or consumption of the DG shall be installed.
The Import/Export Meter and the Production Meter shall be installed next to each other and be easily accessible to CEB personnel, unless otherwise agreed with CEB.
For Distributed Generation (DG) incorporating Battery Energy Storage Systems (BESS), the applicant shall ensure that the system design allows for the installation of all required metering devices necessary to achieve the objectives of the Renewable Energy (RE) scheme under which the application has been submitted.
Where additional meters are required to record internal consumption or auxiliary loads, the applicant shall provide suitable measuring points to enable the installation of the CEB’s meters. These provisions shall be incorporated into the system design to ensure accurate measurement, monitoring, and compliance with the RE scheme requirements.
Testing and commissioning of DG will be done in the presence of the CEB. The CEB shall notify the applicant in advance with a testing and commissioning plan. The applicant shall keep written records of test results and protection settings. The applicant shall regularly maintain their protection systems in accordance with good electrical industry practice.
All electrical apparatus, materials and wiring supplied shall comply with the Electricity Act, the Central Electricity Board Act, Electricity Regulations, this code and the following standards amongst others. Responsibility to comply to relevant standards shall be on the Installer and Applicant.
Note:
| Standard | Description |
|---|---|
| IEC 61215 | Crystalline silicon terrestrial photovoltaic (PV) modules — Design qualification and type approval |
| IEC 61646 | Thin-film terrestrial photovoltaic (PV) modules — Design qualification and type approval |
| IEC 61730-1 | Photovoltaic (PV) module safety qualification — Part 1: Requirements for construction |
| IEC 61730-2 | Photovoltaic (PV) module safety qualification — Part 2: Requirements for testing |
| IEC 61701 | Salt mist corrosion testing of photovoltaic (PV) modules |
| IEC 62804-1 | System voltage durability test for crystalline silicon modules — Design qualification and type approval |
| Standard | Description |
|---|---|
| IEC 62109-1 | Safety of power converters for use in photovoltaic power systems — Part 1: General requirements |
| IEC 62109-2 | Safety of power converters for use in photovoltaic power systems — Part 2: Particular requirements for inverters |
| IEC 62116 | Test procedure for islanding prevention measures for utility connected photovoltaic inverters |
| IEC 61683 | Photovoltaic Systems — Power conditioners — Procedure for measuring efficiency |
| Standard | Description |
|---|---|
| IEC 61727 | Photovoltaic (PV) systems — Characteristics of the utility interface |
| EN 50438 | Requirements for the connection of micro-generators in parallel with public low voltage distribution networks |
| IEC 60364-7-712 | Electrical installations of buildings — Part 7-712: Requirements for special installations or locations — Solar photovoltaic (PV) power supply systems |
| IEC 62446 | Grid connected photovoltaic systems — Minimum requirements for system documentation, commissioning tests and inspection |
| IEC 61724 | Photovoltaic system performance monitoring — Guidelines for measurement, data exchange and analysis |
| IEC 60904-1 | Photovoltaic devices — Part 1: Measurement of photovoltaic current-voltage characteristics |
| IEEE P1547 | Series of Standards for Interconnection |
| Standard | Description |
|---|---|
| IEC 60364-5-55 | Electrical installations of buildings |
| IEC 60664-1 | Insulation coordination for equipment within low-voltage systems — Part 1: Principles, requirements and tests |
| IEC 60909-1 | Short circuit calculation in three-phase ac systems |
| IEC 62305-3 | Protection against lightning — Part 3: Physical damage and life hazards in structures |
| IEC 60364-1 | Electrical installations of buildings — Part 1: Scope, object and fundamental principles |
| IEC 60364-5-54 | Electrical installations of buildings — Part 5-54: Earthing arrangements and protective conductors |
| IEEE C37.90 | IEEE Standard for Relays and Relay Systems Associated with Electric Power Apparatus |
| Standard | Description |
|---|---|
| IEC 61000-3-2 | Limits for harmonic current emissions (equipment input current up to and including 16 A per phase) |
| IEC 61000-3-3 | Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems, for equipment with rated current ≤ 16 A per phase and not subject to conditional connection |
| IEC 61000-6-1 | Generic standard — EMC — Susceptibility — Residential, Commercial and Light Industry |
| IEC 61000-6-3 | Generic standard — EMC — Emissions — Residential, Commercial and Light Industry |
| IEEE 519 | IEEE Recommended practice and requirements for harmonic control of electric power systems |
| Standard | Description |
|---|---|
| IEC 61427 | Secondary Cells and Batteries |
| IEC 62485-2 | Safety requirements for secondary batteries and battery installations |
| IEC 62933 series | Electrical Energy Storage (ESS) Systems Family of Standards |
| IEC 62619 | Safety Requirements for large scale industrial applications (for lithium cells) |
| IEC 63056 | Safety requirements for lithium battery packs and systems for stationary applications |
| IEC 62281 | Safety of primary and secondary lithium cells and batteries during transport |
| IEC 62351 series | Power system security |
| IEC 62620 | Secondary cells and batteries containing alkaline or other non-acid electrolytes |
| IEC 60664-1 | Insulation Co-ordination for equipment within low-voltage systems |
| IEC 60695-1-11 | Fire and Hazard Assessment |
| IEC 62103 | Electronic equipment for use in power installations |
| IEC 61140 | Protection against electric shock |
| IEC 60364 | Electrical installations for buildings |
| UL 1973 / UL 9540 | Certification for battery safety testing or field evaluation to ensure compliance with IEC 62485-2, 61508, 60812 |
| UL 1642 | Standard for safety for lithium-ion batteries |
| IEC 62477-1 | Safety requirements for power electronic converter systems |
| IEC 62109-1 / IEC 62109-2 | Safety of power converters for use in power systems |
| IEC 61000 series | Electromagnetic compatibility (EMC) |
CEB will propose a new version of this Grid Code in case that:
In case of non-compliance with any of the technical provisions in this Grid Code, CEB shall inform the owner in writing of the discrepancies. The DG owner shall have 30 days to rectify the discrepancies.
Failing to do that, CEB shall be entitled to disconnect the DG.
CEB shall be entitled to disconnect the DG without prior notification if the installation conditions are harmful or creates unavoidable risks for the safety.
CEB shall not be responsible for any damage if such disconnection requires the disconnection of other loads associated or connected to the same connection as the SSDG.
Reconnection of the DG shall require that CEB certifies that the installation complies with this Grid Code. Fees applicable shall be the same as for reconnection fee.
After completing the DG installation, the Applicant shall submit the following duly filled and signed “Certificate of Installation” to the CEB (available on the CEB website).
I hereby certify that the installation of the SSDG of Capacity [………] kW, with BESS of [………] kW, [………] kWh situated at address […………………] for Applicant […………………] has been done as per the requirements of the SSDG Grid Code (Ver. 3.0) and as per attached detailed schematic diagram. The inverter trip settings and power limitation parameters have been configured in accordance with the approved settings, as detailed below. Furthermore, the battery system & overall installation is certified as safe for operation at the location where it has been installed on the customer’s premises.
| Equipment | Make/Model | Rating (W & kWh) | Quantity |
|---|---|---|---|
| Photovoltaic Modules | |||
| Inverter | |||
| Battery Energy Storage System |
| Protection Parameter | Settings / Trip Setting | Clearance Time | Trip Indication Provided |
|---|---|---|---|
| Over Voltage (230 V + 10 %) | |||
| Over Voltage (230 V + 6 %) | |||
| Under Voltage (230 V − 6 %) | |||
| Over Frequency (50 Hz + 1.5 %) | |||
| Under Frequency (50 Hz − 6 %) | |||
| Loss of Mains (df/dt — Vector shift) | |||
| Reconnection Time | |||
| Power limitation on Power Exported to Grid (W) | |||
| Line impedance (Ω) | |||
Describe in detail the mode of operation of the DG as configured:
Name of Installer Company:
Name of Certified Installer: (company seal)
Signature of Certified Installer: Date:
Name of Applicant:
Signature of Applicant: Date:
The Certificate for Commercial Operation is completed after successful testing and commissioning of the SSDG installation.
| SSDG Serial No. | Contract Ac. No. | ||
| Name of SSDG owner | |||
| Site Address | |||
| Type of DG | |||
| Capacity of DG | kW | ||
| Capacity of BESS | kW kWh | ||
| Tariff | Date | ||
| Meter | Make/Model & Serial No. | Export Readings | Import Readings | Seal No. | Phase Rotation |
|---|---|---|---|---|---|
| Import/Export Meter | 2.8.0: ____ 2.8.2: ____ 2.8.3: ____ |
1.8.0: ____ 1.8.2: ____ 1.8.3: ____ |
|||
| Production Meter | 2.8.0: ____ 2.8.2: ____ 2.8.3: ____ |
||||
| Consumption Meter | Import: 1.8.0: ____ 1.8.2: ____ 1.8.3: ____ | ||||
I certify that the meter details and readings, as described in the table above, have been taken in my presence and are correct.
Name of SSDG Officer: Signature: Date:
Name of District Officer: Signature: Date:
Name of DG owner/representative: Signature:
Date: