MSDG Grid Code — Greater than 500 kW and not exceeding 2 MW — Version 3.3, August 2024
The purpose of this document is to assist the public to better understand the procedure for application, the requirements of the Grid Code and other related issues regarding Medium Scale Distributed Generation (MSDG).
Any prospective applicant willing to take advantage of the Medium Scale Distributed Generation (MSDG) Scheme is informed that:
The Central Electricity Board’s (CEB) “Grid Code for Medium Scale Distributed Generator (MSDG) – Greater than 500 kW and not exceeding 2 MW”, including any periodic revisions, published on the CEB website, constitute the minimum technical requirements for the connection of an MSDG of size greater than 500 kW and not exceeding 2 MW to CEB’s 22 kV distribution network. The owner of the MSDG may be required to meet additional requirements to ensure that the interconnection meets all local regulations and is safe for use. The requirements set in this Grid Code are based on system conditions that may be subject to change. As such, these requirements shall only be used as a guide, subject to in-depth evaluation. CEB reserves the right to revise this Grid Code at any time. Any person wishing to make use of this Grid Code is invited to contact CEB before proceeding.
The CEB reserves the right to modify such technical specifications and requirements of the MSDG system and the MV switchgear before or during implementation of the MSDG connection process, in order to adhere to the latest operational and safety aspects of the network. The MSDG installation shall abide with the latest MSDG Grid Codes and standards at the time of implementation of the project.
This Grid Code describes the technical criteria and requirements for the connection of distributed generation plants of capacity greater than 500 kW but not exceeding 2 MW to the CEB’s 22 kV distribution network.
The proposed capacity shall be the AC power output from the RE installation. Capacity capping on inverters shall be applicable as appropriate.
This Grid Code caters for the connection to the CEB distribution network and production of electricity by the following Renewable Energy Technologies (RETs):
Note: For the technical criteria and requirements for the connection of MSDG of capacity greater than 50 kW but not exceeding 500 kW, please consult the relevant grid code available on ceb.mu.
The MSDG connection process follows a structured administrative and technical sequence:
The maximum capacity of MSDG that can be connected to a Medium Voltage (MV) feeder is termed the connection capacity of that feeder. Different feeders have different connection capacities depending on the electrical characteristics of the conductor used, the magnitude and temporal variation of feeder loading, and the proposed location of connection.
The feasibility to connect any MSDG to CEB’s 22 kV distribution network will need to be confirmed by an interconnection impact study conducted by the CEB on a case-to-case basis. In addition, the possibility of interconnecting any MSDG facility with variable power output shall be subject to the maximum amount of variable renewable energy-based power generation that can be accommodated while maintaining system stability and security.
Capacity allocation rules:
The interconnection facility required for the MSDG facility consists of:
The MSDG shall function and protect itself within the following range of voltages, currents and frequencies on the CEB grid.
| Parameter | Values |
|---|---|
| Service Voltage | 23.0 kV and 20.5 kV (+4.5% and −7%) |
| System Earthing | Effectively earthed / Non-effectively earthed (contact CEB to confirm) |
| Frequency | 50.75 Hz and 49.25 Hz (50 Hz ± 1.5%) |
| Fault Level | 600 MVA |
| Parameter | Values |
|---|---|
| Service Voltage | 24 kV and 19.8 kV (+9% and −10%) |
| System Earthing | Effectively earthed / Non-effectively earthed |
| Frequency | 52.00 Hz and 47.00 Hz (+4% and −6%) |
| Fault Level | 600 MVA |
The applicant shall construct, install, test and commission the complete 22 kV switchboard as per the default scheme shown in Annex 7 (i.e. both the CEB and Client side). CEB will take ownership of its side after the guarantee period. The switchgear shall have the following characteristics:
| Parameter | Values |
|---|---|
| Nominal system voltage | 22 kV |
| Highest system voltage for equipment | 24 kV |
| Rated voltage | 24 kV |
| Impulse test voltage (1.2/50 μs) | 125 kV peak |
| Rated short circuit capacity | 16 kA rms (1 sec) |
| Electro-dynamic withstand | 40 kA peak |
| Busbar rating | 630 A |
The MSDG interconnection transformer shall be of vector group Dyn11 (Delta on High Voltage side, Star on MSDG side). The delta winding on the CEB side ensures that:
Alternative transformer vector groups may be used subject to CEB approval. The detailed specifications of the interconnection transformer are given in Annex 7. The transformer shall be approved by CEB prior to ordering.
Earthing systems shall be designed, installed, tested and maintained according to BS 7354 and BS 7430. Steps must be taken to prevent the appearance of hazardous step and touch potential when earth faults occur on the 22 kV network. The 22 kV earth electrodes and low voltage earth electrodes shall be adequately separated to prevent dangerous earth potentials being transferred to the low voltage network.
In the event that the applicant is allowed to operate independently and isolated from CEB’s system, the applicant shall ensure that the electrical and protection systems of the facility are designed to support such mode of operation. Safety of personnel and integrity of equipment shall be guaranteed at all times during both parallel and isolated modes of operation.
The coordination and selectivity of the protection system must be safeguarded even with the entrance of new generation into the system. The settings of all protections shall be proposed by the promoter and accepted by CEB. The protection system shall provide protection against fault occurring on both CEB’s network and the MSDG facility, including short circuit, earth faults and overloading conditions, and shall also prevent islanding of the CEB distribution feeder.
All protection relays shall be numeric type with event logging and disturbance recording capabilities. The MSDG owner shall maintain the protection system and keep spares of all relays used in the MV switchgear.
The Interconnection Protection Scheme shall consist of: (i) Multi-step instantaneous/time-delayed and IDMT overcurrent (50/51); (ii) Multi-step instantaneous/time-delayed and IDMT earth fault (50N/51N); (iii) Neutral Voltage Displacement (59N).
Protections 50/51 and 50N/51N shall act on the CEB Interconnection Circuit Breaker (CB1). The 59N shall act on all client’s outgoing circuit breakers.
The MSDG shall cease to energise CEB’s network within 0.5 seconds of the formation of an island. The following protection functions and settings are required:
| Parameter | Symbol | Trip Setting | Clearance |
|---|---|---|---|
| Overvoltage | U>> | Vφ-φ + 9% | 0.2 s |
| Overvoltage | U> | Vφ-φ + 6.0% | 1.5 s |
| Undervoltage | U< | Vφ-φ − 10% | 3.0 s |
| Overfrequency | f> | 52 Hz | 0.5 s |
| Underfrequency | f< | 47 Hz | 3.0 s |
| Loss of Mains — ROCOF | LoM | 2.5 Hz/s | 0.5 s |
| Loss of Mains — Vector Shift | LoM | 10° | 0.5 s |
The anti-islanding protection shall act on CB4 (MSDG circuit breaker). For MSDG ≥1 MW, inter-tripping facility using fiber optic cables or wireless communication is also required (see Section 3.6.5).
An inter-tripping and interlocking system shall ensure that tripping of the CEB 22 kV Circuit Breaker (on fault, open locally or remotely) shall inter-trip ALL the Client outgoing 22 kV Circuit Breakers instantaneously. Closing of the CEB 22 kV Circuit Breaker is ONLY allowed if ALL Client 22 kV Circuit Breakers are in the open position.
The inter-tripping scheme shall be designed and pre-wired such that tripping of the interconnecting feeder circuit breaker in the CEB 22 kV substation results in the tripping of CB1. For solar PV MSDG ≥1 MW:
For MSDG using RE technologies other than solar PV, generation occurs throughout the day and night; hence, CB1 shall be opened remotely irrespective of the time of the fault.
The watchdog function of the protection relay shall issue an alarm and trip the circuit breaker on which the protection relay normally acts in case of a malfunction. For MSDG ≥500 kW, this alarm signal (if required by CEB) shall be transmitted to the interconnecting CEB substation via fiber optic channel or wireless communication.
For MSDG >500 kW, the applicant shall submit to CEB appropriate settings for grading and discrimination of the interconnecting protection (22 kV circuit breaker, CEB side) with the upstream CEB substation protection. The applicant shall also submit to CEB the fault contribution (both single-phase to earth and three-phase) from the generating plant on the 22 kV side.
Additionally, Table 4 below shows the NVD trip settings for the Neutral Voltage Displacement relay required for all MSDG >500 kW connected via MV switchgear:
| Parameter | Symbol | Trip Setting | Clearance Time |
|---|---|---|---|
| Neutral Voltage Displacement (59N) | NVD | When neutral point voltage displacement on the 22 kV side exceeds 10% of 22 kV/√3 (1,270 V) | 5.5 s |
The following requirements are additional to the mandatory protections above and apply to all MSDG irrespective of the generation technology used:
Following a protection-initiated disconnection, the MSDG is to remain disconnected from the network until the voltage and frequency at the supply terminals has remained within the nominal limits for at least 3 minutes. Automatic re-connection is only allowed when disconnection was due to operating parameters being outside the normal operating range. If disconnection was caused by malfunctioning of any devices within the MSDG installation, manual re-connection with CEB authorisation is required.
An online UPS is required to ensure that the protection, measurement, control and communication systems operate without interruption for a minimum duration of 3 hours after loss of CEB power supply. In the event of loss of the secured auxiliary supply, all Client 22 kV circuit breakers shall be tripped until remedial actions are taken.
For MSDG ≥1 MW, all equipment used for the transmission of signals and commands (PLC, modem, router, etc.) between the MSDG site and CEB System Control shall be supplied from a separate UPS to that of the protection systems.
The alarm and trip facilities shall have local indication and, for MSDG ≥1 MW, an additional set of potential-free contacts for onward transmission of the alarm/trip signals to the CEB Substation. For MSDG ≥1 MW, a local SCADA system shall be installed to allow monitoring and control of the MSDG installation.
External indicator lamps shall be installed for MSDG >500 kW to indicate parallel operation with the CEB distribution network: a lighted red lamp shall indicate parallel operation; a lighted green lamp shall indicate isolated operation.
Panel instrumentation shall include transducer-fed voltmeter, ammeter, MW, MVAr (indicating import and export), and appropriate test blocks for current and voltage circuits.
The MSDG owner shall install communication equipment for secured transfer of operating data and protection and control signals. For MSDG ≥1 MW, a fiber optic cable link shall connect the MSDG plant to the corresponding 22 kV substation (as per Annex 9). The applicant bears the full cost of procurement, installation, testing, commissioning and maintenance of the communication system.
The following data shall be transmitted in real time from the Generation Facility to the CEB Substation:
For MSDG >1 MW, remote control commands shall also be provided (Load Break Switch OPEN/CLOSE, CB1 open/close).
Where wireless communications are used, the system shall meet the following minimum requirements:
The CEB meter, CTs and VTs shall have at least the following accuracy classes:
| MSDG Installation | Connected to LV Network | Connected to MV Network |
|---|---|---|
| Not exceeding 500 kW | Class 1 | Class 0.5 |
| Greater than 500 kW and not exceeding 2 MW | — | Class 0.5 |
| Greenfield | — | Class 0.2 |
The CEB meter shall have separate registers for import and export of energy. All CEB metering circuits shall be totally separate from the MSDG promoter’s circuits. Toroidal CTs will not be accepted for HT metering purposes.
A second production meter shall be installed by CEB inside the MSDG installation. All meters and related equipment (CTs, VTs, TTB) shall be housed in a secured metering cabin fitted with a 13A power socket protected by a 2A circuit breaker and fed from a secured source of supply. The MSDG promoter shall first seek CEB’s approval for CT/VT specifications before ordering and send equipment to CEB’s Meter Lab Section for testing prior to installation.
MSDG ≥1 MW shall facilitate a generation forecast to CEB (day-ahead, hourly values by default). MSDG <1 MW does not need to communicate a generation forecast.
MSDG ≥1 MW shall submit annual preventive maintenance plans to CEB for approval, with monthly updates and at least 15 days’ advance notice for any planned changes. For corrective maintenance, CEB shall be notified within 3 hours of the occurrence. MSDG <1 MW is not required to submit maintenance plans.
Maintenance works or faults on the feeder may prevent the MSDG from exporting. No compensation shall apply for loss of generation due to preventive and corrective maintenance in CEB’s network. CEB shall communicate its maintenance plans to MSDG promoters ≥500 kW before the planned maintenance action takes place.
CEB personnel shall strictly abide by the “CEB T&D Safety Rules” in compliance with the Occupational Safety and Health Act 2005. The MSDG promoter shall:
The MSDG shall comply with the requirements of the EMC Directive and in particular the product family emission standards.
A CEB-standard MSDG warning label (Figure 1) shall be affixed at the following locations:
Up-to-date information must be displayed at the MSDG installation, including:
Each MSDG installation shall display an information plate showing: (a) manufacturer’s name or trade mark; (b) type designation or identification number; (c) rated power; (d) nominal voltage; (e) nominal frequency; (f) phases; (g) power factor.
The MSDG shall be installed in accordance with the manufacturer’s instructions. The installer shall consider all aspects including: maximum demand and generator output; type of earthing arrangement; nature of the supply; external influences; compatibility, maintainability and accessibility; protection against electric shock and thermal effects; protection against overcurrent; isolation and switching; selection and installation issues.
The installer shall affix a label indicating the next scheduled maintenance and inform CEB to update the MSDG register. The installer shall be skilled in the field of MSDG installations and possess an MQA-approved qualification or equivalent in electrical installation and renewable energy installations acceptable to CEB.
All electrical apparatus, materials and wiring shall comply with the Electricity Act, the CEB Act, Electricity Regulations, this Code and the following standards (latest editions apply):
Installers are required to ensure that all proposed equipment has the capabilities to implement all the requirements of the MSDG Grid Code, especially the requirements stipulated in this chapter.
The MSDG shall remain connected to the distribution system for system voltage dips on any or all phases, where the distribution system voltage measured at the point of common coupling remains above the boundary shown in Figure 2 below. MSDG ≥1 MW shall be able to provide fault-ride through capability.
In addition to remaining connected, the MSDG shall provide active power in proportion to retained voltage and maximise reactive current injection to the distribution system for at least 3 seconds, or until the distribution system voltage recovers to within the normal operational range. The LVRT curve shall be coordinated with the under-voltage protection settings (Table 5).
MSDG ≥1 MW shall provide power-frequency response to contribute to the stabilisation of the grid frequency. Under normal system frequency ranges, the MSDG shall operate at maximum available active power output. The MSDG shall reduce power output above a system frequency of 50.5 Hz at a gradient of 40% per Hz of the instantaneously available power. The output power is only allowed to increase again once frequency returns to 50.5 Hz or below. Above 52 Hz the MSDG shall disconnect within 0.5 seconds. Below 47 Hz for longer than 0.5 seconds, the MSDG is permitted to disconnect.
MSDG ≥1 MW shall be equipped with reactive power control functions that are mutually exclusive — only one mode active at a time:
All MSDG ≥500 kW shall be designed to supply rated power for power factors ranging between 0.95 lagging and 0.95 leading, available from 20% of rated power.
The MSDG facilities and equipment shall not cause excessive voltage excursions nor introduce excessive distortion to the sinusoidal voltage or current waves.
The MSDG installation shall not cause abnormal flicker beyond the limits defined in IEEE 519 at the Point of Common Coupling.
The MSDG system output at the PCC shall comply with IEEE 519. The IEEE 519 recommendation is to be applied at the PCC, not to downstream equipment.
Step voltage changes caused by the connection and disconnection of generating plants at the distribution level shall not exceed ±3% for infrequent planned switching events or outages and ±6% of the nominal voltage of 22 kV for unplanned outages such as faults.
The interconnection system shall have surge withstand capability (oscillatory and fast transient) in accordance with IEC 62305-3. The design of control systems shall meet or exceed the requirements of IEEE C37.90.
The contribution to the level of voltage unbalance at the PCC from any MSDG installation shall be less than or equal to 1.3%.
MSDG ≥1 MW shall have controlled ramp up/down: positive ramp rate only during start-up; negative ramp rate during shutdown of the MSDG facility.
The applicant shall perform the testing and pre-commissioning phases of the MSDG as per relevant standards. The applicant shall keep written records of all test results and protection settings. The interconnection protection of the MSDG shall be regularly tested and maintained. Ad-hoc tests may be required by CEB for purposes such as harmonic assessment, voltage rise, protection operation following system changes, and fault investigation.
For Greenfield projects, the applicant shall submit testing and pre-commissioning procedures and plans to CEB for approval at least 3 months prior to the Scheduled Commercial Operation of the MSDG Facility.
Pre-commissioning tests shall be performed in the presence of CEB and shall include at minimum:
After satisfactory testing and pre-commissioning and submission of the Certificate of Installation, CEB will perform tests to ensure the facility is compliant with Section 4.4 of this Grid Code.
Given the size and complexity of the MSDG installation, testing and pre-commissioning shall be performed by a Registered Professional Engineer. The RPE shall inspect and test the installation for compliance with existing requirements and report results to CEB. The MSDG Owner shall then submit a duly signed Certificate of Installation. Upon compliance, CEB shall prepare a Certificate of Compliance confirming that the installation complies with the requirements of this Grid Code, has been found fit for connection to the Grid, and is commissioned after the signature of the Connection Agreement.
In case of non-compliance with any of the technical provisions in this Grid Code, CEB shall inform the owner in writing of the discrepancies. The MSDG owner shall have 90 days to rectify the discrepancies. Failing to do that, CEB shall be entitled to disconnect the MSDG installation.
CEB shall be entitled to disconnect the MSDG facility without prior notification if the installation conditions are harmful or create unavoidable risks for safety. CEB shall not be responsible for any damage if such disconnection requires the disconnection of other loads connected to the same connection as the MSDG.
Reconnection of the MSDG shall require that CEB certifies that the installation complies with this Grid Code. Fees applicable shall be the same as the standard reconnection fees.
A Certificat de Consignation is required before any work can be performed on either side of the 22 kV switchgear panel. The competent person performing switching operations shall certify the operations carried out on this approved form and remit the original to his CEB counterpart, who may then proceed with the work in accordance with the applicable safety procedures.
The certificate includes fields for: date and time; name of competent person; description of switching operations performed; equipment switched (panel numbers, CB designations); signatures of the client and CEB representatives; and confirmation that appropriate isolation, padlocking and warning signs are in place.
The MSDG will be connected to CEB’s 22 kV network through a High Voltage switchgear and metered on the high-voltage side. The applicant shall bear fees for processing applications and preparation of cost estimates for network construction or modification. The list of fees is available on the CEB website.
Fees include: Processing fee; Connection Fee; Engineering Review / Distribution Study; Revision of Estimate. Network construction / modification costs are determined after the engineering review.
The applicant/installer shall submit a duly signed certificate (with the company’s header and seal) to CEB. The MSDG installation shall be certified by a Registered Professional Engineer (CRPE Mauritius). The certificate shall include:
This certificate confirms that the MSDG installation with an installed capacity of [kW], situated at [address] in the name of [Applicant/Company name] bearing Serial No. [MSDGX/XX/XXX] has been found compliant with the requirements of the MSDG Grid Code by the CEB Representatives hereunder and is fit for connection to the Grid. The installation shall be commissioned after the signature of the Connection Agreement.
The Certificate of Compliance is signed by representatives from:
The following single-line diagram shows the required 22 kV switchgear arrangement at the MSDG interconnection facility, with the demarcation between CEB equipment and MSDG Owner equipment:
Responsibilities and costs for the interconnection facility:
The following diagram shows the typical high voltage switchgear panel and protection guideline for inverter-based MSDG generation (Annex 8a):
The fiber optic communication system shall connect the MSDG facility to the 22 kV feeder substation for all MSDG ≥1 MW. The system shall transmit all required status, measurement, alarm and control signals as specified in Section 3.11 of this Grid Code. Detailed communication data points, protocols and interface specifications shall be agreed with CEB prior to procurement and installation. All costs of procurement, installation, testing, commissioning and maintenance of the communication system are borne by the MSDG promoter.